The Chief Executive Officer of the Uganda Electricity Transmission Company Limited (UETCL), Eng. Richard Matsiko together with the Ag. Managing Director of the Uganda Electricity Distribution Company Limited (UEDCL), Eng. Joselynne R. Rwabwogo have conducted an inspection of the ongoing Greater Kampala Metropolitan Transmission System Improvement Project to assess the progress of works.
The project is currently 90.57% complete, with the Maya (Buloba) 220/132/33kV Substation fully completed and other major components progressing well. Ongoing works include the re-conductoring of critical 132kV transmission lines and upgrades to existing substations, activities that require planned outages to ensure the safety of personnel, the general public and the integrity of the transmission system during construction.
The project, financed by the Japan International Cooperation Agency (JICA) through a JPY 13 billion (about USD 83.3 million) concessional loan to the Government of Uganda, is being implemented by UETCL. The contractor of the project is the consortium of China Machinery Engineering Corporation (CMEC) and Toyota Tsusho Corporation (TTC). This project is meant to strengthen the capacity and reliability of the electricity transmission network serving the Greater Kampala Metropolitan Area.
Speaking during the inspection, Eng. Matsiko, acknowledged the inconvenience experienced by customers and expressed appreciation for the public’s patience.
“We understand the inconvenience these planned outages have caused to businesses and residents across the Kampala Metropolitan Area. However, these interruptions are a necessary part of delivering a stronger, more reliable transmission network capable of meeting the city’s rapidly growing electricity demand. We are now in the final stages of implementation and are working diligently to complete the remaining works as quickly and safely as possible.”
The Kampala Metropolitan Area remains Uganda’s largest electricity consumer, with increasing demand driven by urbanization, industrialization, and commercial growth estimated at 15% annually. The existing transmission infrastructure is operating close to its design limits, making strategic investments essential to improve network resilience, reduce congestion, and enhance the quality and reliability of electricity supply.
The project includes;
- Theconstruction of new substations at Maya and Mukono
- Upgradingof existing substations at Kawaala, Mutundwe, and Bujagali,
- Installationof new transmission lines, re-conductoring of existing 132kV transmission lines.
- Thedeployment of a mobile substation at Namungoona to strengthen supply reliability across the metropolitan area.
Eng. Joselynne R. Rwabwogo, emphasized the importance of the project in improving electricity service delivery to consumers.
“While customers are experiencing temporary interruptions today, the long-term benefits will be significant. This investment will improve the stability and quality of power supply, reduce network constraints, and enable us to serve customers more efficiently as demand continues to grow,” Eng. Rwabwogo, noted.
She sympathized with customers for the planned outages, which she noted were necessary during the project implementation period.
“Unfortunately, during the UETCL grid improvement works, there is intermittent supply as a result. We appeal to our customers to bear with us during this period for a great and better service delivery at the end of the day,” Rwabwogo, said.
She observed that the improved network resilience will facilitate UEDCL’s ambitious access project that targets to add up to 300,000 new customers annually.
Once completed, the Greater Kampala Metropolitan Transmission System Improvement Project will significantly increase transmission capacity within the metropolitan area, improve grid resilience, reduce the risk of widespread outages, and support major economic developments, including industrial expansion and strategic infrastructure such as the planned Buloba Pump Station under Uganda’s oil and gas development programme.
UETCL and UEDCL reaffirm their commitment to keeping the public informed throughout the remaining phase of the project and appreciate the continued understanding and cooperation of customers as Uganda invests in a stronger electricity transmission network to support sustainable national development.
UETCL is responsible for bulk purchase of electricity from power generators and bulk sale of electricity to power distributors through high voltage transmission lines. The company operates the High Voltage Transmission Grid (HVTG) above 33kV including the load dispatch system at the National Control Centre.
The Uganda Electricity Distribution Company Limited (UEDCL) was formed in 2001 pursuant to the Electricity Act, 1999 (as amended 2022), following the unbundling of the Uganda Electricity Board (UEB). As the national electricity distributor, UEDCL is mandated to own, operate and maintain the electricity distribution network below 33kV across the country.