      Nabeta, Namuganza Extends Endorsement Drive for Gen to Namutumba, Cite Continuity

      October 23, 2026

      PLU Luuka District Endorses Gen Muhoozi’s 2031 Presidential Bid

      October 13, 2026

      Iganga PLU Leaders Endorse Muhoozi for 2031 Presidency

      September 29, 2026

      Muhoozi Appoints Fadil Twalla as New PLU Secretary General ,Drops Kabanda

      June 15, 2026

      Why not wait for Court Decision? NUP Declares next move if George Musisi’s Victory gets nullified

      June 14, 2026
    • BUSINESS

      AYA Group Strengthens Its Position as a Ugandan Investment and Industrial Development Group

      October 23, 2026

      NCBA, Nedbank Complete Landmark Transaction, Creating a Powerful East African Financial Services Growth Platform

      October 23, 2026

      UNCST Moves to Support Uganda’s Manufacturer of automotive spare parts Standard Waves Ltd

      October 20, 2026

      dfcu Bank Strengthens Dialogue with SMEs in Namanve and Mukono 

      October 19, 2026

      UEDCL Launches Nationwide Blood Donation Drive, assures customers of improved supply reliability

      October 17, 2026
    • SPORTS

      dfcu Bank Hails Success of Inaugural Serena Captain’s Putter Golf Tournament

      September 29, 2026

      The NCBA Junior Golf Series 2026 Tees Off

      August 28, 2026

      Businessman Sudhir Ruparelia’s Group Donates Shs 25m Support to Lwakataka’s Rally Comeback

      August 23, 2026

      KCB Bank Uganda Hosts 2nd Edition of KCB East Africa Golf Tournament Under the Theme “Roar on the Green.”

      June 29, 2026

      NCBA Bank Launches Uganda Leg of the 2026 NCBA Golf Series

      June 11, 2026
    • HEALTH

      TMR International Hospital Wins Best Healthcare Service Provider ,Best Digital Health Innovation Awards

      October 20, 2026

      The Soul of My foot Print 2026 Free Medical Camp Benefits Hundreds in Buikwe, Jinja Areas

      October 18, 2026

      UEDCL Launches Nationwide Blood Donation Drive, assures customers of improved supply reliability

      October 17, 2026

      Uganda Celebrates World Food Day 2026 With a Push For Agri-Tech and Resilient Food Systems

      October 17, 2026

      424 Mutungo residents receive free health services as dfcu-Rotary Uganda partnership expands

      October 1, 2026
    Facebook X (Twitter) Pinterest WhatsApp TikTok
    The Analyst Uganda
    Home»BUSINESS»Attorney General warns against terminating contract of Entebbe Expressway toll operator
    BUSINESS 12,006 Views

    Attorney General warns against terminating contract of Entebbe Expressway toll operator

    Daniel MuwanguziBy Daniel MuwanguziAugust 29, 2026Updated:August 29, 2026No Comments5 Mins Read12,006 Views
    Facebook Twitter Pinterest LinkedIn Tumblr Email
    Attorney General warns against terminating contract of Entebbe Expressway toll operator
    Share
    Facebook Twitter LinkedIn Pinterest Email
    Share This Story

    Uganda risks a costly international arbitration if it terminates the contract of a private operator managing toll collection and operations on the Kampala-Entebbe Expressway, the Attorney General has warned.

    This week, parliament’s committee on physical infrastructure, chaired by Mwine Mpaka, called for the immediate termination of French company EGIS Road Operation S.A., which was contracted by the Uganda National Roads Authority (Unra) on April 13, 2021, to operate and maintain the expressway.

    Demo

    Dissatisfied with EGIS’s performance, the committee made at least 14 recommendations, including transferring operations and toll collection on the 24-kilometre expressway to the ministry of Works and Transport.

    The committee also wants the Uganda Revenue Authority (URA) to take over toll collection, arguing that direct government control would reduce the cost of private contractual arrangements and free up more resources to service the debt incurred to finance the expressway.

    EGIS’s five-year contract, valued at Shs 122.86 billion, took effect on May 24, 2021 and provides for a possible extension of up to 24 months, subject to satisfactory performance.

    However, in a response presented to parliament, deputy Attorney General Jackson Karugaba Kafuuzi said government cannot simply terminate a valid contract without first establishing that the operator has committed a persistent breach and following the termination procedure provided for in the agreement.

    Kafuuzi told parliament that EGIS must first be formally notified of any breach and given 14 days to remedy it. Where improvement works are delayed, the contract provides for liquidated damages and reductions in payments.

    Termination on grounds of persistent failure, he said, can only arise after specified contractual thresholds have been reached.

    Kafuuzi instead advised the ministry of Works and Transport to undertake a comprehensive assessment to establish whether EGIS’s failures meet the contractual threshold for termination.

    EGIS’s obligations extend beyond toll collection to include road-safety improvements, lighting, tolling infrastructure, an independent traffic monitoring system, an automatic vehicle classifier and systems for controlling overloaded vehicles.

    The committee found that several of these obligations had not been fully implemented.

    MPs cited incomplete installation of the independent traffic monitoring system and automatic vehicle classifier, inadequate carriageway lighting and road-reserve fencing, as well as shortcomings in the high-speed weigh-in-motion systems.

    The committee argued that the failures justified taking the expressway back under direct government management. Although Kafuuzi acknowledged that failure to complete works within agreed timelines constitutes a contractual breach, he stressed that a breach does not, by itself, trigger immediate termination.

    The legal response also challenges Parliament’s concerns over the extension of a related contract involving Pinnacle Security Limited. The committee recommended an investigation into the former permanent secretary over what it described as an illegal Shs 36.3 billion extension allegedly granted without the Attorney General’s approval.Legal

    The Attorney General’s office disputes that finding, saying the ministry of Works and Transport extended the contract through a letter dated May 20, 2026, with the extension running from May 24, 2026 to May 24, 2027.

    According to the legal opinion, the extension was provided for under Clause PCC 39.1 of the original agreement and did not introduce additional expenditure.

    The Shs 36.3 billion cited by the committee, the office said, formed part of the original contract price, making the extension a “no-cost extension” that did not require fresh legal clearance.

    The office also rejected claims that the novation agreement transferring the contract to Pinnacle had not been legally approved, saying the Solicitor General cleared it on April 22, 2026.

    Kafuuzi said satisfactory performance remained a condition for the extension and that responsibility for assessing performance against the agreed key performance indicators rested with the ministry.

    Parliament’s proposal to hand toll collection to URA also faces a legal hurdle. The Attorney General says the Roads Act places responsibility for toll collection on the relevant roads authority, in this case the ministry of Works and Transport.

    As a result, the function cannot simply be transferred in its entirety to URA without legislative changes, although the two institutions can collaborate in administering the tolling system.

    The ministry also cannot immediately take over the expressway’s operations while the existing operating contract remains legally enforceable. Rather than an immediate takeover, the Attorney General supports a forensic audit of the EGIS and Pinnacle revenue collection systems from their inception.

    The audit is intended to establish whether government lost revenue that should have been used to service the loan that financed the expressway.

    The legal response points to the latest information systems audit, finalized on August 19, 2026, which identified several weaknesses in the expressway’s operations.

    These include high operating costs, weak governance systems, network-security vulnerabilities, incomplete overload-control systems, limited payment options, manual vehicle classification, unsupported toll exemptions and prolonged lane closures.

    The Attorney General also addressed concerns over free toll passes issued at the Busega Toll Plaza.

    Parliament’s inquiry found that free passes worth Shs 314.355 million had been issued between January 2022 and June 2026. The Attorney General said recovery of the money from the contractor may not be straightforward because, although the Roads Act specifies categories of vehicles and persons exempt from toll payments, the contract also provided for free passes for certain ministry and operator staff.

    The legal opinion said the irregularity was attributable to government and therefore could not automatically be recovered from the private operator.

    The ministry and Attorney General’s office have proposed regularising the exemptions through appropriate statutory instruments.

    The Attorney General also urged caution over calls for criminal investigations and prosecution of officials involved in the procurement, management and oversight of the expressway.

    The office said determining whether offences were committed should be left to the relevant authorities, noting that Article 120 of the Constitution gives the DPP authority over investigations and prosecutions.

    It further noted that previous Auditor General Reports had not identified irregularities in the procurement of EGIS. The proposed forensic audit, the office said, should first establish whether financial losses occurred and quantify any loss before responsibility is assigned.

    Attorney General warns against terminating contract of Entebbe Expressway toll operator
    Share. Facebook Twitter Pinterest LinkedIn Tumblr Email
    Previous ArticleEABC Strengthens Export Capacity of Uganda’s Service Sector through LIFTED Project Coaching
    Next Article Uganda Private Sector Calls for Stronger Action to Unlock EAC Trade and Investment
    Daniel Muwanguzi

    Related Posts

    Nabeta, Namuganza Extends Endorsement Drive for Gen to Namutumba, Cite Continuity

    October 23, 2026

    AYA Group Strengthens Its Position as a Ugandan Investment and Industrial Development Group

    October 23, 2026

    Deputy Mufti Bukenya Cited in Shs1.2 billion Gold Fraud

    October 23, 2026
    Leave A Reply Cancel Reply

    Economy News
    NEWS
    NEWS POLITICS By Daniel Muwanguzi32,001 ViewsOctober 23, 2026

    Nabeta, Namuganza Extends Endorsement Drive for Gen to Namutumba, Cite Continuity

    By Daniel MuwanguziOctober 23, 20260

    The Patriotic League of Uganda (PLU) Busoga regional coordinator Mr Samuel Nabeta has joined State…

    AYA Group Strengthens Its Position as a Ugandan Investment and Industrial Development Group

    October 23, 2026

    Deputy Mufti Bukenya Cited in Shs1.2 billion Gold Fraud

    October 23, 2026
    Top Trending
    NEWS
    NEWS POLITICS By Daniel Muwanguzi32,001 ViewsOctober 23, 2026

    Nabeta, Namuganza Extends Endorsement Drive for Gen to Namutumba, Cite Continuity

    By Daniel MuwanguziOctober 23, 20260

    The Patriotic League of Uganda (PLU) Busoga regional coordinator Mr Samuel Nabeta…

    NEWS
    NEWS Africa BUSINESS By Daniel Muwanguzi32,012 ViewsOctober 23, 2026

    AYA Group Strengthens Its Position as a Ugandan Investment and Industrial Development Group

    By Daniel MuwanguziOctober 23, 20260

    AYA Group of Companies, under the leadership of Executive Chairman Mohammed Mohammed…

    NEWS
    NEWS East Africa By Daniel Muwanguzi12,301 ViewsOctober 23, 2026

    Deputy Mufti Bukenya Cited in Shs1.2 billion Gold Fraud

    By Daniel MuwanguziOctober 23, 20260

    The Deputy Mufti of Uganda, Muhammad Haruna Bukenya, has been summoned to…

    Subscribe to News

    Get the latest sports news from NewsSite about world, sports and politics.

    Advertisement
    Demo

    Head Office
    Church Road, Muyenga Zone A , Off Muyenga _ Bukasa Road
    Makindye _ Kampala
    📞 ‪+256744763464‬/ +56765431389

    📧 Email: analystuganda25@gmail.com
    Website:
    We're social. Connect with us:

    Facebook X (Twitter) YouTube WhatsApp
    Categories
    • Africa (103)
    • BUSINESS (526)
    • East Africa (93)
    • ENTERTAINMENT (58)
    • Featured (34)
    • FOOD & SCIENCE (39)
    • HEALTH (95)
    • National (169)
    • NEWS (739)
    • Oil & Gas (1)
    • OPINIONS (43)
    • POLITICS (45)
    • SPORTS (40)
    • Technology (10)
    • TOURISM (31)
    • Uncategorized (106)
    • World (21)
    Blog Posts

    Nabeta, Namuganza Extends Endorsement Drive for Gen to Namutumba, Cite Continuity

    October 23, 2026

    AYA Group Strengthens Its Position as a Ugandan Investment and Industrial Development Group

    October 23, 2026

    Deputy Mufti Bukenya Cited in Shs1.2 billion Gold Fraud

    October 23, 2026

    NCBA, Nedbank Complete Landmark Transaction, Creating a Powerful East African Financial Services Growth Platform

    October 23, 2026
    Facebook X (Twitter) YouTube WhatsApp TikTok
    © 2026 The Analyst Uganda. CRAFTED By Accord Communications Ltd.

    Type above and press Enter to search. Press Esc to cancel.

    imunify-bot-check